+27(0)21 863-5000 tender@casidra.co.za

RFQ: PROVIDE AND INSTALL ELECTRICAL FENCING AGAINST THE EXISTING WIRE FENCE

Location:

Franschhoek, Western Cape

Post Date:

2022-12-09 09:54:00

Closing Date:

2022-12-13 12:00:00

Contact Person:

Ms. C Makhuvha

Contact Email:

cmakhuvha@casidra.co.za

Bidding on this tender has ended

Tender Details

RFQ: FRANSCHHOEK: HORNBILL GROUP: PROVIDE AND INSTALL ELECTRICAL FENCING AGAINST THE EXISTING WIRE FENCE

This document is not for sale. Any entity that requests payment must be reported at the contact person indicated in this tender.

GENERAL REQUIREMENTS

The farm where all the work has to be done is called “Klein Goederust” and is situated in Franschhoek with Google Coordinates – 33⁰ 53’ 22,93” S and 19⁰ 05’ 22,72” E. The quoted amount will be a lump sum bid and must include labour and machinery.  As the works are emergency repairs, the successful bidder must have the capacity to start the works within 7 (seven) days after the day of appointment.

Conditions that may pose a risk:  

Security for materials and equipment must be supplied. The Contractor must put all necessary precautions in place to work under these conditions.

The person appointed by the Client to act as the Project Manager is C. Makhuvha and is responsible for the project management of this contract and can be reached at 079 507 3737 and email address is cmakhuvha@casidra.co.za.

All technical enquiries can be referred to Mr A.J. Otto at (021) 863 5000 or 083 410 7736.

The scope of works will include:

Provide and install electrical fencing against the existing wire fence

Documents for the purpose of this bid include:

  1. Standard Conditions of Contract can be viewed on the Casidra website at casidra.co.za.
  2. Price Form, Bill of Quantities and Schedules (Form CBD 3.1 (Lump Sum)
  3. Scope of Works (Form CBD 4)
  4. PPP Evaluation Form (Form CBD 5.1 (80/20)
  5. Bank Entity Form (Form CBD 7), unless the banking details of the company indicate “verified” on the Central Supplier Database (CSD).
  6. Registration on the CSD for all suppliers is compulsory and registration numbers must be supplied.
  7. Local content documents.
  8. Drawings: “Sketch A”

In accordance with Casidra’s Preferential Procurement Policy, this bid as further indicated in CBD 5.1is subject to:

  • a functionality compliance test;
  • B-BBEE certified bids will receive preferential scores;
  • Local production and content

This bid include goods from a designated sector,( Steel products and components for construction (incl. wire) and Electrical & Telecom cables) only locally produced goods, services or works, or locally manufactured goods with a stipulated minimum threshold for local production and content will be considered. SBD 6.2 and Annex C, D and E documentation apply and must be completed and handed in with this bid.

The successful bidder will be required to fill in and sign a written Contract Form (CBD 8). Included are a penalty clause of R  500/calendar day that apply for late completion of works and a 10% retention fee for 3 months not bearing interest.

RFQ DEADLINE:  The closing date for the request for quote is 13 December 2022 strictly at 12H00.

SUBMISSION OF RFQ

All RFQ documents to be uploaded onto the Casidra RFQ/Tender portal. No e-mailed or hard copy documents will be accepted.

The following documents (including fully completed and signed CBD forms numbered 1 to 7 as supplied) must be valid for a period of 60 calendar days after closure of the bid and submitted as a bid packet:

Document number Document description Action required/comment 
CBD 1 General requirements Signed
CBD 2.1 Conditions to submit bid Signed
CBD 3.1 Price form (lump sum) Complete, sign
CBD 3.1 Experience Proof of previous work and contact details of three work-related references that are qualified to comment on work. Compulsory
CBD 3.1 Rates Unit rates for the works on the forms as supplied Compulsory
CBD 3.1 Changes Indication if any changes are proposed in scope of works and cost implication. If required
CBD 4 Scope of works Signed
CBD 5.1(80/20) PPP Evaluation form Complete, sign
CBD 7 Bank Entity form (Not needed if “verified” on CSD)(Banking details as provided by bank) Complete, bank stamp
TCC of principle and sub-contractors Registration and verification of Tax Clearance on CSD. Compulsory
BEE B-BBEE Certificate or Sworn Affidavit (as applicable, see CBD 5 for detail) Original affidavit or certified copy certificate/Valid/not compulsory
Company profile Detailed company profile including the core competencies of personnel and subcontractors Compulsory
COIDA Letter of good standing of the Contractor in terms of COIDA Valid/ compulsory
OHS Plan Occupational Health and Safety Plan approved by the Client Valid/ Proof after appointment
CI Proof of construction insurance Valid/ Proof after appointment
Local Content forms Fully completed SBD 6.2 and annexure C compulsory
SAEFIA Proof of registration with SAEFIA Compulsory
Electrical registration for main supply Electrical contractor for the electrical installation must supply proof of Electrician registration (SAEFIA) Compulsory
Warranty Provide copy of warranty offered Compulsory